MAISONInterior Design

HDB flat · Hougang · North-East region

Tanjong Tree Residences @ Hougang Renovation & Interior Design

Tanjong Tree Residences @ Hougang is an HDB project in Hougang, with a listed address at Hougang Street 13. Our project file describes it as near completion, lists a November 2021 phase, and carries a third-party 2026 completion note. This entry is not officially confirmed. Official HDB roadshow resources, checked in our file on 7 November 2026, do not confirm a project-wide TOP or key date, and key appointments are unconfirmed. Unit counts and any completion year or month are therefore left out of the facts below. If you have an HDB key letter, use that. The November 2021 phase note is not treated as a key date. This page sets out what is on file and how to plan your Tanjong Tree Residences @ Hougang renovation.

Tanjong Tree Residences @ Hougang at a glance

Type
HDB flat
Developer
HDB (listed in our project file, not officially confirmed)
Area
Hougang
Region
North-East
Address (as listed)
Hougang Street 13

This project is not marked officially confirmed in our project file. Unit counts, tenure and completion or key dates from third-party trackers have been left blank until they can be cited from HDB.

Facts from the sources listed at the end of this page.

Planning your Tanjong Tree Residences @ Hougang interior

Hougang Street 13 sits in a mature north-eastern town. Owners who are close to keys usually want a first fit-out that can start as soon as the permit is in hand: a fitted kitchen, full-height wardrobes, an entry shoe cabinet, and a living-room storage wall, designed from the approved plan rather than from a guessed layout. Maison specifies built-in carpentry, not flat-pack furniture, and we can work in a wide room view or in closer shots of a wardrobe or a kitchen run. No official floor plan is on file, so typologies and room sizes are not listed.

Kovan Wellspring is the other Hougang page in this batch; a tracker month for that project was withdrawn, and it should not be used as a date guide for Tanjong Tree. We will not invent walking times to Hougang town, to Kovan, or to any MRT station. Check your block, facing and the HDB renovation rules before you plan blinds, a bench or any hacking.

After keys, inspect defects, measure, and obtain the HDB renovation permit before fabrication. A moderate, non-structural carpentry scope is often planned at six to ten weeks on site after access and approvals, as an editorial figure only. WhatsApp Maison with your approved plan and any key letter you have. We are not affiliated with HDB.

Planning your Tanjong Tree Residences @ Hougang renovation

Defects check at handover

  • Report defects within 30 days of key collection, before renovation starts (HDB move-in guide). The Defects Liability Period runs 1 year from key collection.
  • Check floor and wall tiles for hollow or chipped pieces, plaster for cracks, and paint for stains.
  • Test every door, window, lock, tap, floor trap, light point and power socket.
  • Report through the QR code in your Welcome Kit or your project's Building Service Centre, with photos.

What the rules allow

  • Use a contractor listed in HDB's Directory of Renovation Contractors; they can apply for the permit for you.
  • A permit is needed for works such as removing floor finishes, raising floor levels in wet areas, or hacking or altering walls.
  • For the first 3 years, toilet wall and floor finishes in a new BTO flat cannot be removed. New tiles can be overlaid.
  • General works: Monday to Saturday, 9am to 6pm. Noisy works: Monday to Friday, 9am to 5pm. No works on Sundays or public holidays.
  • Household shelter walls must not be hacked or drilled. Windows need a BCA-approved window contractor; air-conditioners need a BCA-trained installer.

Rules change, so we check the current version for your unit before we quote. Full bto key collection renovation guide

From keys to move-in

  1. 01

    Before keys 4 to 8 weeks

    Layout, 3D drawings and an itemised quotation, so work can start as soon as defects are reported.

  2. 02

    Keys + first 2 weeks 1 to 2 weeks

    Defects inspection and reporting, permit application, measurements on site.

  3. 03

    Wet works and electrical 2 to 3 weeks

    Tile overlays, screed or vinyl, wiring and plumbing points.

  4. 04

    Carpentry 3 to 5 weeks

    Built in the factory while wet works run on site, then installed.

  5. 05

    Finishing 1 to 2 weeks

    Painting, lights, glass, cleaning and a handover walk-through.

Tanjong Tree Residences @ Hougang renovation FAQ

Is the completion or key date for Tanjong Tree Residences @ Hougang confirmed?

Not in our project file. This project is not officially confirmed, so unit counts and tracker dates have been left blank. If you have an HDB key-appointment letter, use that.

Do you have the Tanjong Tree Residences @ Hougang floor plan?

No official floor-plan or site image is on file for this page, so none is published here. Please send your approved HDB unit plan.

Do I need an HDB renovation permit?

Yes, for the usual HDB renovation works. After keys, inspect defects, then apply for the permit with a registered contractor before carpentry is fabricated.

What should I send Maison?

Your approved floor plan, unit type if you have it, and a key date if one is already in writing. WhatsApp us at https://wa.me/6593391185.

Sources

Facts checked against the sources on file, 11 November 2026.

Maison Interior Design is an independent interior design firm. We are not appointed by, or affiliated with, the developer, HDB or the building's owner. We have not worked at Tanjong Tree Residences @ Hougang unless our portfolio says so. Concept pictures are AI-generated style concepts, not photos of a finished unit.

Talk to Maison

Planning your Tanjong Tree Residences @ Hougang renovation?
WhatsApp Maison

WhatsApp Maison with your unit type, approved floor plan and key date (if you have one).