Planning a renovation
BTO Renovation Order of Works: What to Do First After Getting Your Keys
The BTO renovation order of works matters after key collection. Our BTO key collection page says the weeks after you collect your keys decide how smoothly the rest goes. This article walks through the points that page covers.

Defects check at handover
HDB's move-in guide, as quoted on our BTO page, says new BTO flats have a 1-year Defects Liability Period from your key collection date. It also says you must report defects within 30 days of key collection, before renovation starts.
So the defects check comes before any renovation work.
Permit
Our BTO page says "some works need a permit before anyone lifts a hammer." Maison handles the HDB renovation permit application as part of the process, and helps with a renovation loan application too. Permit rules can change, so check them with HDB.
Plan your points before carpentry
Plan lighting points, power points and data points before carpentry starts. The reason our page gives is that cables then hide inside the cabinets.
Stages and durations
Our BTO page lists these stages and durations:
- Before keys: 4 to 8 weeks
- Keys + first 2 weeks: 1 to 2 weeks
- Wet works and electrical: 2 to 3 weeks
- Carpentry: 3 to 5 weeks
- Finishing: 1 to 2 weeks
These are the durations the site states. Your own timeline is not covered here.
Two rules to keep in mind
- Our page says noisy work is only allowed on weekdays.
- Our page says that for the first 3 years HDB does not allow you to remove wall or floor finishes in the toilets, so new tiles go over the old ones.
These are HDB rules and can change, so check the current rules on the HDB website before you plan.
See it before it is built
Our home page says every room is drawn in 3D before work starts. For how we put a quotation together, see Itemised renovation quotation. For the full list of what we do, see Services.